A novel heuristic method for flexible job-shop scheduling problem with sequence-dependent setup time, transportation time and machine efficiency constraints

  • Oksydan Sp. z o.o.

Wyniki badań: Wkład do czasopismaArtykułrecenzja

Abstrakt

This paper presents a novel heuristic approach to the Flexible Job-Shop Scheduling Problem (FJSP), incorporating sequence-dependent setup and transportation times, as well as machine efficiency constraints. The objective of the optimization was to minimize the total makespan of the job scheduling process. To solve this problem, a computational tool was developed, which implemented a new heuristic method based on a sequential algorithm, alongside selected priority assignment rules (FIFO, LIFO, LPT, SPT, EDD, LWR). The effectiveness of the generated schedules was evaluated using multiple criteria. Comparative numerical results were presented for various problem parameters and priority rules, demonstrating the performance and advantages of the proposed approach.

Język oryginałuangielski
Strony (od–do)485-504
Liczba stron20
CzasopismoArchives of Control Sciences
Tom35
Numer wydania3
Identyfikatory DOI
Status publikacjiOpublikowano - 2025

Obszary tematyczne ASJC Scopus

  • Inżynieria sterowania i systemów
  • Modelowanie i symulacja
  • Sterowanie i optymalizacja

Fingerprint

Zanurz się w tematy badawcze publikacji „A novel heuristic method for flexible job-shop scheduling problem with sequence-dependent setup time, transportation time and machine efficiency constraints”. Razem tworzą niepowtarzalny odcisk palca.

Cytowanie